One of the most widely used contractual structures in Turkish real estate practice is the arrangement under which a landowner transfers a share of their property to a contractor in return for the contractor constructing a building on that land and delivering a portion of the completed units back to the landowner. This arrangement, known in Turkish law as the kat karşılığı inşaat sözleşmesi or arsa payı karşılığı inşaat sözleşmesi, has become a standard mechanism in urban construction across Turkey. It allows landowners who lack the capital to finance construction to become property owners without paying cash, while contractors gain access to land without purchasing it outright. The financial logic of the arrangement is straightforward, but the legal structure underlying it is considerably more complex.

This type of contract does not have a dedicated statutory definition in Turkish law. It emerged from contractual practice and developed through decades of Court of Cassation case law into a well-established legal instrument. Its regulation draws simultaneously from multiple bodies of law, including the Turkish Code of Obligations, the Turkish Civil Code, the Condominium Ownership Law No. 634, and the zoning and construction permit legislation administered by municipal authorities.

Legal Nature of the Contract

Turkish courts and legal doctrine consistently classify the construction in exchange for flats contract as a hybrid, bilateral obligatory contract. It combines elements of two distinct legal categories: the works contract, governed by Articles 470 and following of the Turkish Code of Obligations, and the contract for the preliminary sale of immovable property, governed by Article 237 of the Turkish Code of Obligations and Article 706 of the Turkish Civil Code.

The works contract dimension of the arrangement imposes on the contractor the obligation to produce a result — specifically, to construct a building in accordance with the agreed project and technical specifications and to deliver the completed units to the landowner. The preliminary sale dimension imposes on the landowner the obligation to transfer specified shares of the land to the contractor in exchange for this performance. Each party bears obligations toward the other, and neither party can demand performance from the other without first having performed or being ready to perform their own obligations.

Article 470 of the Turkish Code of Obligations: A works contract is a contract by which the contractor undertakes to produce a work and the principal undertakes to pay a price for it.

Article 237 of the Turkish Code of Obligations: A preliminary contract for the sale of immovable property must be executed in an official form. Any preliminary contract that does not comply with this requirement is void.

Formal Requirements and Consequences of Non-Compliance

Because the construction in exchange for flats contract contains an element of immovable property transfer — specifically, the landowner’s promise to transfer land shares to the contractor — it is subject to the formal requirements that Turkish law imposes on contracts for the sale or preliminary sale of real property. Under Article 706 of the Turkish Civil Code and Article 237 of the Turkish Code of Obligations, contracts whose purpose is the transfer of immovable property rights must be executed in an official form.

In practice, this means that the construction in exchange for flats contract must be drafted and signed before a notary public. A written contract signed privately by the parties, without notarial authentication, does not satisfy the formal requirement and is void as a matter of law. The Court of Cassation has consistently applied the position that a formally defective contract creates no rights or obligations for either party, and that defenses based on unjust enrichment rather than the contract itself must be pursued when the parties have already partially performed under a void agreement.

Article 706 of the Turkish Civil Code: The transfer of immovable property ownership requires that the agreement of the parties be recorded in an official deed. Any agreement that does not comply with this formal requirement is void.

One important qualification to the strict invalidity rule arises from the principle of good faith. Where one party has performed substantially under an informally concluded contract and then seeks to invoke the formal defect to avoid its own obligations, courts have on occasion applied the principle of venire contra factum proprium to prevent such conduct. However, the application of this principle is fact-specific and cannot be relied upon as a substitute for the formal requirements.

Any amendment to a validly concluded construction in exchange for flats contract that alters the obligations of either party — such as changing the distribution of units, modifying the construction timeline, or adjusting the specifications — must itself comply with the same formal requirements as the original agreement. A subsequent oral or private written amendment to a notarially concluded contract does not bind the parties.

Obligations of the Landowner

The primary obligation of the landowner under a construction in exchange for flats contract is to deliver the land in a condition that is suitable for construction and to transfer the agreed land shares to the contractor at the contractually specified times. The delivery of the land must be genuine and effective, meaning that the landowner must ensure that any existing structures on the land are demolished, that the land is clear of encumbrances that would impede construction, and that all necessary permissions for construction are either already in place or obtainable.

The landowner must also cooperate with the contractor’s efforts to obtain construction permits. In Turkey, building permits are issued by the relevant municipality and require the submission of architectural and engineering projects prepared by licensed professionals. The landowner’s cooperation in signing permit applications and granting the contractor the powers necessary to apply for permits is an essential auxiliary obligation under the contract.

Where the landowner fails to deliver the land on time or in suitable condition, or refuses to provide the necessary cooperation for permit applications, the contractor may invoke the rules on creditor default under the Turkish Code of Obligations. In such cases, the contractor may grant the landowner a reasonable additional period to perform, and if the landowner fails to perform within that period, the contractor may either withdraw from the contract or claim damages in lieu of performance.

Obligations of the Contractor

The contractor’s primary obligation is to construct the building in accordance with the agreed project, technical specifications, and construction timeline, and to deliver the completed units to the landowner free from defects. The standard of construction is measured against the specifications set out in the contract and, where the contract is silent on a particular point, against the standard that would be expected for a building of the relevant type in the relevant market.

Article 471 of the Turkish Code of Obligations: The contractor is obliged to perform the work with care and diligence commensurate with the trust placed in them, and to refrain from any conduct that would harm the principal. The contractor must perform the work personally or under their supervision, and shall be liable for the work of their assistants.

The contractor must also comply with all applicable zoning regulations, construction standards, and building permit conditions. A building that is constructed in violation of the permit or in breach of zoning rules is an unlawful structure in the eyes of Turkish law, and the contractor cannot be regarded as having performed their obligations under the contract by delivering such a structure. Where the violation is severe enough that the building cannot be legalized through subsequent proceedings, the landowner is entitled to terminate the contract, and the contractor loses the right to demand any compensation for work performed.

The contractor’s obligation to obtain the occupancy permit, known as the yapı kullanma izni or iskan belgesi, is an important ancillary obligation. This permit is issued by the municipality upon completion of the building and confirms that the structure conforms to the approved project and is fit for its intended use. Delivery of units without the occupancy permit is generally treated as defective delivery in Turkish case law, since the units cannot be used for their intended purpose without this document.

Land Registry Annotation

To protect the contractor’s rights under the contract against the risk that the landowner might sell or encumber the land before the project is completed, the contract may be annotated in the land registry. This annotation, known as tapuya şerh, puts third parties on notice of the contractor’s existing rights over the property. A purchaser or creditor who acquires rights over the land after the annotation is registered cannot claim ignorance of the contractor’s position, and the contractor’s rights under the contract are therefore enforceable against such third parties as well.

Similarly, where the contractor has already received title to certain land shares but the project is subsequently terminated, the landowner may seek the cancellation of those title registrations through a title deed cancellation and re-registration lawsuit, known as tapu iptal ve tescil davası. The success of such an action depends on the grounds for termination and the degree of completion of the project at the time of termination.

Defective Construction and the Contractor’s Liability

Where the contractor delivers the building or individual units with defects — whether structural, technical, or cosmetic — the landowner has the remedies available to a principal under the works contract provisions of the Turkish Code of Obligations. These remedies include demanding that the contractor remedy the defect at the contractor’s expense, demanding a reduction in the contractor’s share of units proportionate to the diminution in value caused by the defect, claiming compensation for damages caused by the defect, or, where the defect is so serious that it renders the unit useless for its intended purpose, withdrawing from the contract entirely.

Article 475 of the Turkish Code of Obligations: Where the work is defective, the principal may demand that the defect be remedied at no additional cost, claim a proportional reduction in the price, or withdraw from the contract if the defect renders the work worthless or unacceptable. The right to claim damages is reserved in all cases.

The landowner must notify the contractor of any apparent defects within a reasonable time after discovering them. Failure to give timely notice may result in the loss of the right to rely on those defects. For hidden defects that only become apparent after delivery, the notification period runs from the time the defect is discovered.

Termination of the Contract and Its Consequences

The termination of a construction in exchange for flats contract is one of the most litigated areas in Turkish real estate law. The consequences of termination depend significantly on how much of the construction work has been completed at the time the contract is ended.

Where the contractor has not yet begun construction or has completed only a minor portion of the work, termination operates retroactively, meaning that the parties are restored to their pre-contract positions. The landowner recovers any land shares that were transferred to the contractor, and the contractor has no claim for the value of work performed, since the incomplete performance does not enrich the landowner to any measurable degree.

Where the contractor has completed a substantial portion of the construction — typically assessed as a majority of the projected scope of work — retroactive termination would produce an inequitable result, because the landowner would obtain the benefit of the partially completed construction without compensating the contractor. In such cases, Turkish courts apply the principles developed by the Court of Cassation’s Plenary Decision of January 25, 1984, which established that the completion rate of the construction determines the applicable legal regime. Where significant work has been done, the termination operates prospectively rather than retroactively, and the contractor is entitled to receive compensation for the work performed on a unjust enrichment or equitable basis, while the landowner retains the right to recover land shares that exceed the contractor’s equitable entitlement.

Where the contractor becomes insolvent during the construction process, the landowner may terminate the contract and reclaim transferred land shares through a title deed cancellation lawsuit. However, if the contractor has already sold units to third-party purchasers, the situation becomes considerably more complex, as the rights of those purchasers must also be accounted for. Courts examine whether those purchasers acted in good faith and whether the land registry annotation or other public records should have put them on notice of the landowner’s potential claims.

Penalty Clauses and Delay Compensation

Most well-drafted construction in exchange for flats contracts include a penalty clause, known as cezai şart, which specifies the amount payable by the contractor for each day or month of delay in completing the construction and delivering the units. This clause operates independently of the requirement to prove actual loss and gives the landowner a simpler remedy for delays without needing to quantify lost rental income or other consequential damages.

Courts retain the authority to reduce an excessive penalty clause to a reasonable level under Article 182 of the Turkish Code of Obligations, particularly where the contractor can demonstrate that the landowner suffered no substantial loss or that the delay was attributable in part to factors beyond the contractor’s control. Nevertheless, the penalty clause remains an important protective mechanism that landowners should ensure is clearly formulated and realistically calibrated to the project.

Real Estate Lawyer in Istanbul – Attorney Ozan Soylu

Attorney Ozan Soylu is a practicing lawyer based in Istanbul, advising landowners, contractors, and property purchasers in matters relating to construction in exchange for flats contracts, title deed disputes, and real estate litigation under Turkish law. His practice covers contract drafting and review, land registry annotation proceedings, defective construction claims, and termination and title cancellation lawsuits before Turkish civil courts.

Legal consultancy and representation services are provided with a dedicated approach for foreign nationals. To submit your questions, contact us.


 

author avatar
Av. Ozan Soylu
Av. Ozan Soylu is a Turkey-based attorney practicing in Istanbul, representing both local and international clients in a wide range of legal matters. His areas of practice include family law, criminal defense, real estate and property disputes, inheritance law, debt collection and enforcement proceedings, citizenship applications, and legal services for foreigners in Turkey. He provides strategic and solution-oriented legal representation with a strong focus on cross-border matters, international clients, and complex legal disputes.